Gill Wilson, Growth Strategy
and Funding Manager confirmed that copies of the Monitoring and
Performance Report and a covering report had been circulated to
members of the Board. Members were reminded that the City of
Lincoln Council (CoLC) were required to submit monitoring returns
to the Department of Levelling Up Housing and Communities (DLUHC)
every six months to cover expenditure, progress, risks, outputs and
outcomes.
The next report due was for
the period 1 April 2023 to 30 September 2023 and submission was
required by Monday 4 December 2023. The monitoring return required
sign off by the Council’s Chief Finance Officer and the Chair
of the Lincoln Town Deal Board. In addition, there was the
requirement that the document be circulated to all members of the
Lincoln Town Deal Board. The main points highlighted for the
Monitoring and Evaluation Performance Report to DLUHC
were:
- HEAT, The Drill and Store of
Stories had a combined value of £2.3M and had reached
completion by September 2023
- Lincoln Central Market and
Lincoln Be Smarter were projects that remained on programme with a
combined value of £7.9M
- There had been slippage
across the remainder of the projects, however all were expected to
be completed by March 2026. There were no issues to raise regarding
deliverability
- Spend was under forecast but
within percentage tolerances acceptable to DLUCH
- Expenditure was expected to
accelerate as the delayed projects started and completed
delivery.
Evidenced Outputs to be
reported included:
- 1 x new Cultural
Facility
- 1 x new Community
Hub
- 1 x Historic building
renovated and restored for reuse as commercial space
- 22 x Full Time
jobs
- 106 x Temporary jobs
supported
- Capacity for an additional
125 people to be trained with 243 trainees enrolled overall at the
new facilities
Other reported benefits
included:
- HEAT project had led to the
creation of 4 new businesses
- The Store of Stories,
Community Grocery membership continued to increase with 1055 new
members since opening and 14,030 customer visits a month -
approximately £584 per week. The project had also evidenced
that through the service offered, it had been able to support 1413
children from the impact of food poverty.
- Cost risk was to be reported
in respect of all pre-tender projects. Such risks had been managed
and mitigated by projects through detailed pre-tender cost
analysis, evaluation assurance and cost engineering
- No projects had raised any
issues of non-deliverability due to raised project costs, but all
projects had reported cost pressures to some degree. Regular
meetings and updates with the projects aimed to ensure that any
issues were identified promptly
- Raised mitigated scores had
been identified with Wigford Way and Greyfriars
- Progress had been made since
September 2023 on the delivery plans for Wigford Way as reported
under Item 4 of the supplement pack.
Comments and questions were
invited from members of the Board. Discussions concluded with
confirmation that Focus Consultants had been commissioned for the
creation of a mid-term evaluation report which would likely be
completed by the end of January 2024.
RESOLVED that:
- the Board agreed that the
Monitoring and Evaluation Performance Report be submitted to DLUHC
by 4 December 2023.
- Officers be tasked with the
arrangement of an online evaluation session with Focus Consultants,
for the benefit of Members not in attendance.
- The Mid-Term Evaluation
report created by Focus Consultants be presented to the Board in
March 2024.