Gill
Wilson, Growth Strategy and Funding Manager confirmed that copies
of the Monitoring and Performance Report and a covering report had
been circulated to members of the Board. Members were reminded that
the City of Lincoln Council (CoLC) were required to submit
monitoring returns to the Department of Levelling Up Housing and
Communities (DLUHC) every six months to cover expenditure,
progress, risks, outputs and outcomes.
The
next report due was for the period 1 April 2023 to 30 September
2023 and submission was required by Monday 4 December 2023. The
monitoring return required sign off by the Council’s Chief
Finance Officer and the Chair of the Lincoln Town Deal Board. In
addition, there was the requirement that the document be circulated
to all members of the Lincoln Town Deal Board. The main points
highlighted for the Monitoring and Evaluation Performance Report to
DLUHC were:
Programme
- HEAT, The Drill and Store of Stories had a combined value of
£2.3M and had reached completion by September
2023
- Lincoln Central Market and Lincoln Be Smarter were projects that
remained on programme with a combined value of
£7.9M
- There had been slippage across the remainder of the projects,
however all were expected to be completed by March 2026. There were
no issues to raise regarding deliverability
Expenditure
- Spend was under forecast but within percentage tolerances
acceptable to DLUCH
- Expenditure was expected to accelerate as the delayed projects
started and completed delivery.
Outputs and Outcomes
Evidenced Outputs to be reported included:
- 1 x
new Cultural Facility
- 1 x
new Community Hub
- 1 x
Historic building renovated and restored for reuse as commercial
space
- 22
x Full Time jobs
- 106
x Temporary jobs supported
- Capacity for an additional 125 people to be trained with 243
trainees enrolled overall at the new facilities
Other reported benefits included:
- HEAT project had led to the creation of 4 new
businesses
- The
Store of Stories, Community Grocery membership continued to
increase with 1055 new members since opening and 14,030 customer
visits a month - approximately £584 per week. The project had
also evidenced that through the service offered, it had been able
to support 1413 children from the impact of food
poverty.
Risk
- Cost risk was to be reported in respect of all pre-tender
projects. Such risks had been managed and mitigated by projects
through detailed pre-tender cost analysis, evaluation assurance and
cost engineering
- No
projects had raised any issues of non-deliverability due to raised
project costs, but all projects had reported cost pressures to some
degree. Regular meetings and updates with the projects aimed to
ensure that any issues were identified promptly
- Raised mitigated scores had been identified with Wigford Way and
Greyfriars
- Progress had been made since September 2023 on the delivery
plans for Wigford Way as reported under Item 4 of the supplement
pack.
Comments and questions were invited from members of the Board.
Discussions concluded with confirmation that Focus Consultants had
been commissioned for the creation of a mid-term evaluation report
which would likely be completed by the end of January
2024.
RESOLVED that:
- the
Board agreed that the Monitoring and Evaluation Performance Report
be submitted to DLUHC by 4 December 2023.
- Officers be tasked with the arrangement of an online evaluation
session with Focus Consultants, for the benefit of Members not in
attendance.
- The
Mid-Term Evaluation report created by Focus Consultants be
presented to the Board in March 2024.