Minutes:
Amanda Stanislawski, Audit Manager:
a. presented the Annual Internal Audit Report to the Audit Committee for comments.
b. explained that the purpose of the Annual Internal Audit Report as outlined at Appendix A was to provide a summary of Internal Audit work undertaken during 2022/23, timed to support the Annual Governance Statement by providing an opinion on the organisation’s governance, risk management and internal control environment
c. highlighted that:
· The three areas, Governance, Risk, Internal Control and Financial Control were working well having no concerns that significantly affected the governance framework and successful delivery of the Council priorities.
· Internal control was assessed as performing adequately – some improvements were identified over the Council’s Governance, Risk and Control Framework. This was due to a number of factors which included there being two Limited Assurance reports this year and an increase in the number of high recommendations. There was however, a significant reduction in the number of outstanding actions from prior years.
d. explained that there had been no restrictions on the scope of the work to be undertaken; the reduction in time due to the Auditor and Principal Auditor leaving had been covered through the employment of consultants and removal of items from the plan.
e. advised that the performance of the Internal Audit Service remained good with 91% of the revised plan being completed and a high level of customer satisfaction. Performance had been impacted due to capacity in some areas including audit span and the ability to chase management responses.
f.
gave an update on the current staffing level within
Internal Audit and explained that the post of Principal Auditor and
Auditor were currently being advertised for recruitment.
g. invited members questions and comments.
Comment: Expressed concerns about the
difficulties in recruiting and retaining staff.
Response: Recruitment in Local Government was currently a
national problem. Recruitment was currently taking place to try and
appoint a Principal Auditor and Auditor. Back stop measures such as
external resource and a casual auditor had been employed to ensure
that audits would be completed.
Questions: Commented that only 14 out
of 59 recommendations had been implemented following an audit,
leaving a substantial amount of recommendations outstanding, and
asked for more details.
Response: A lot of the Audits were completed later in the
year, therefore there had not been time to implement the
recommendations, they were not due for implementation yet and the
deadlines had not been missed.
Question: Asked if an exit interview
took place when a member of staff left the Authority and further
asked if the statistics regarding the reasons why staff were
leaving could be shared with Audit Committee.
Response: An exit interview was offered to staff, but these
were optional. The data collected was shared with the Corporate
Management Team. This information did not fall within the scope of
Audit Committee and suggested that it be raised at Performance
Scrutiny Committee.
Question: Referred to the Critical activities identified by
Management as having a low level of assurance in relation to
Combined Assurance and asked what PCIDSS stood for.
Response: Clarified that the acronym was for Payment Card
Industry Data Security Standard.
Question: Further asked for details on the issues with the
activities listed in the report.
Response: There were issues for a variety of reasons some
included:
· Legal – Issues with capacity
· Elections – New regulations
· Events and Culture – The Christmas Market
· Tree Management – Would be circulated following the meeting
· Leisure – Covid 19 and increased energy costs
Question:
Asked if performance
monitoring and management were still taking place whilst staff
worked from home.
Response: Yes, performance was being monitored and the
management style had been adapted for home working.
Question: Asked if risk management training would take place in 2022/23.
Response: Risk management training had been scheduled for 16 August 2023 for all members.
Question: Asked why there were delays in obtaining responses to draft reports.
Response: The biggest problems were the staffing issues in the areas themselves who were having to prioritise their work.
Question:
Referred to IT Asset Management and asked if a
physical inventory list was being completed.
Response: A response would be circulated following the
meeting.
RESOLVED that the contents of the report and appendices be noted
Supporting documents: