Issue - meetings

Charterholme Housing Phase 1 and Wider Update

Meeting: 20/01/2025 - Executive (Item 74)

74 Charterholme Delivery - Eastern Access and First 52 Homes (ONE@CHARTERHOLME) pdf icon PDF 295 KB

Minutes:

Purpose of Report

 

1.    To provide an update on the delivery of the Eastern Access, including the rail overbridge, and the agreements which were in place with Network Rail and Lincolnshire County Council.

 

2.    To provide an update on the development of the first 52 homes and to set out options for the management of the residual public open spaces within this phase.

 

3.    To outline the ongoing work with partners in relation to the detailed design of the site wide infrastructure and the prospective funding arrangements to support its delivery

 

Decision

 

1.    That the progress with the delivery of the Eastern Access and the provisions that had been agreed to assist in managing the longer-term risks for the Council be noted.

 

2.    That the proposals for the management of the retained areas in respect of the first 52 homes, namely that these were to be retained by the Council and a service charge levied as set out within the officer’s report be approved.

 

3.    That the work towards a potential future funding package to support accelerated delivery be noted.

 

Alternative Options Considered and Rejected

 

To transfer the residual green spaces and common areas of the land into a Management Company, which would ultimately be managed independently of the Council, with costs recovered via a service charge on the new home-owners.

 

Reasons for the Decision

 

Conditional approval by Executive in July 2024 to progress with the delivery of the eastern site access from Tritton Road to include a vehicle and multi-user bridge oversailing the railway line was subject to final approval of the technical designs and legal agreements being in place with Network Rail and Lincolnshire County Council (LCC) regarding construction, adoption, maintenance and the granting of rights for the resulting infrastructure This had now been secured. The City and County Council had entered into respective bridge agreements with Network Rail to cover the arrangements for construction and adoption of the asset in September 2024, allowing the City Council to enter into contract with John Graham Construction Ltd for delivery of the bridge and access road, which was progressing well.

 

The City Council had also entered into a Section 278 Agreement with LCC which permitted carriageway works to the existing highway at Tritton Road to form the bell-mouth and a new signalised junction to serve the site once housing development commenced. Additional works to tie in with Tritton Road and Dixon Street junctions was also part of this scope of works.

 

In addition to the bridge works, the City Council had now entered into a Development Agreement with Lindum Developments Limited for the delivery of the first 52 homes, following the Executive decision in July 2024 and final approval of the legal drafting and associated finances, in line with that decision.

 

Works had now commenced on site for the first phase of 19 homes, which were due to be completed in summer/autumn 2025 onwards.

 

In preparation for the marketing and sale of these first homes, the development site had now  ...  view the full minutes text for item 74